The 125,000 bpd Warri refinery resumed production this week after maintenance and is expected to run at 60,000 bpd.
The Port Harcourt complex will start ramping up over the next two weeks but only the newer of the two plants at the site is functional and at 90,000 bpd versus its 150,000 bpd capacity.
The last refinery to restart will be the northern Kaduna refinery as it will take about two more weeks to repair the pipeline bringing crude from the oil-rich delta in the south.
Athough there are repairs to be made requiring about $1 billion investment,with the creaky refineries springing back to life, Nigeria aims to produce at least 20 per cent of its petrol needs.
Ian Udoh, the group executive director of refining and petrochemicals, said that he expected to receive six cargoes a month of Nigerian Bonny Light and Escravos crude oil to run 180,000 barrels per day (bpd) or 40 percent, of Nigeria’s total refining capacity.
He expected to produce 8 million litres a day of gasoline, accounting for about 20 percent of Nigeria’s estimated consumption.
During the last eight months, no crude was sent to the refineries, said the company contracted to deliver the oil. A government document also showed that the deliveries stopped last year but a month earlier, in October.
Nigeria has wholly depended on subsidised fuel imports and crude-for-product swap agreements and suffered acute fuel shortages in May.
President Muhammadu Buhari is keen to stop the dependence on fuel import.
The government’s anti-corruption and security services are investigating the intricate structure of oil swaps deals. The crude in those contracts is taken out of the domestic allocation.
Due to the dilapidation of pipeline infrastructure, refineries depend on sea deliveries. Since 2011, Nigeria based PPP Fluid Mechanics Ltd has been delivering crude for the state Nigerian National Petroleum Corp and an official there said no explanation was given for the supply halt.
“We were contracted to deliver 1.65 million barrels a month to Warri and 3.12 million barrels to Port Harcourt,” the official at PPP Fluid Mechanics said.
Nigeria’s refineries have been neglected for years, operating sometimes just at 20 percent capacity, and did not even have functioning gasoline producing units at one point, Udoh said.
He added that up to $1 billion would be needed to replace just one of the key pipelines and an overhaul of the jetties was necessary to receive more vessels.
*Adapted from Reuters
View Comments (1)
I think that's a strong word to use when they were closed for repair and maintenance, and some of them are older than PMB's first stint in office, so it's not like these are modern refineries we are talking about.